Introduction
Picture this Estimate at completion : You’re presenting your project’s financials to stakeholders with a sleek line chart showing funded and billed amounts over time. It’s clear, it’s concise—but it’s missing something critical. What if you could show not just where the project is, but where it’s headed? Enter Estimate at Completion (EAC)—a game-changing metric that transforms static reports into proactive tools for cost control and decision-making.
For project managers with 8-30 years of experience, you’ve likely mastered the art of tracking budgets. But integrating Estimate at Completion (EAC) into your visuals takes it to the next level—offering stakeholders a crystal-clear view of projected outcomes. Here’s a quick tip to start: Add EAC as a dashed line on your chart to instantly highlight budget risks. In this 2000+ word guide, we’ll walk you through how to do it, why it matters, and how it can elevate your project reporting to strategic heights.
What Is Estimate at Completion (EAC)?
EAC Defined
EAC combines actual costs to date with an estimate of remaining costs. It’s dynamic, adjusting as your project evolves—unlike the static Budget at Completion (BAC). Think of it as your financial GPS, guiding you through risks and opportunities.
How to Calculate EAC
Choose the method that fits your project:
- EAC = AC + (BAC – EV): Assumes past performance continues (AC = Actual Cost, BAC = Budget at Completion, EV = Earned Value).
- EAC = BAC / CPI: Uses Cost Performance Index (CPI) for trend-based forecasts.
- EAC = AC + Bottom-Up Estimate: Re-estimates remaining work for precision.
Tip: For volatile projects, combine methods—use CPI for trends and bottom-up for major scope shifts.
Why EAC Matters for Project Financial Visibility
Spotting Risks Early
Example: A PM notices EAC trending 10% over budget mid-project and cuts low-value tasks, saving thousands.
Empowering Stakeholder Decisions
Stakeholders with 8-30 years of experience don’t want surprises—they want data to act on. EAC shows how delays or changes impact the bottom line, making approvals or trade-offs strategic.
Pro Tip: Plot multiple EAC lines (best/worst case) to spark richer discussions.
Step-by-Step: Adding EAC to Your Line Chart
Setting Up the Chart
- X-Axis: Time (e.g., weeks, months).
- Y-Axis: Dollar Amount (or currency).
- Series to Plot:
- Funded Amount: Solid line—your approved budget baseline.
- Billed Amount: Solid line—actual costs to date.
- EAC: Dashed line—projected final cost.
Styling for Clarity
Make it visually intuitive:
- Funded Amount: Solid green (stability).
- Billed Amount: Solid blue (progress).
- EAC: Dashed red (risk alert).
Tip: Add annotations (e.g., “Scope Change”) at EAC jumps to explain shifts to stakeholders.
Success Story: EAC Saves a Tech Project from Overruns
The Action:
At the next review, the PM highlighted the EAC trend, proposed trimming a non-essential feature, and recalculated Estimate at Completion (EAC) to align with the funded amount. Stakeholders approved on the spot.
The Result:
The project closed at $510K—2% over budget instead of 15%. Without EAC, the overrun would’ve blindsided the team.
Key Insight: Estimate at Completion (EAC) turns data into decisions—vital for PMs with years of experience managing high-stakes projects.
Best Practices for Presenting EAC to Stakeholders
A great Estimate at Completion (EAC) chart isn’t just data—it’s a story. Here’s how to make it resonate with seasoned leaders.
Add Context with Markers
Annotate key events—like scope approvals or risks—on the chart. A spike in EAC tied to “Vendor Delay” tells a clearer tale than numbers alone.
Showcase Scenarios
Plot multiple EAC lines:
- Best Case: Optimistic CPI (e.g., costs stabilize).
- Worst Case: Pessimistic trends (e.g., delays persist).
- Most Likely: Your standard EAC.
Example: A PM shows a $50K range, prompting stakeholders to prioritize cost-saving measures.
Simplify the Narrative
Tip: Start presentations with, “Here’s where we’re headed—let’s discuss how to stay green.”
Advanced Tips: Taking EAC to the Next Level
For PMs with 8-30 years of experience, these extras can sharpen your EAC game.
Link EAC to Earned Value
Example: A low CPI (0.9) bumps EAC up—prompting resource reallocation.
Automate EAC Updates
Conclusion
Estimate at Completion (EAC) isn’t just a number—it’s your secret weapon for proactive project reporting. For project managers with 8-30 years of experience, integrating EAC into line charts offers:
- Early warnings on budget risks.
- Clear, visual forecasts stakeholders trust.
- Strategic insights to steer projects home.
Start small: Calculate EAC for your next report, add it as a dashed line, and watch how it shifts the conversation. You’ve spent years honing your craft—now let EAC amplify your impact.